Procurement Policy to accompany Procurement Process
-
The requestor MUST complete the Material Requisition Form (MRF, for materials/sub-contractors) completely detailing full products/services specifications and drawings in hard copy. The technical data can be supplied in electronic format.
-
The head of the relevant department then reviews the form to ensure completion and either approves or rejects the request. If form is incomplete, the form will be returned.
-
Forms MUST be sent signed hard copy directly to the Procurement Department Head.
-
Once all quotations accompanied with technical data have been collected and a Material Comparison Sheet prepared (MCS), the Procurement Department will review and check the quotes against the project budget with the Department Head.
-
A procurement committee consisting of the relevant Department Head, Procurement Head and Deputy General Manager will discuss, negotiate and shortlist the final selection of supplier quotes.
-
Further negotiations may take place as necessary by the Deputy General Manager to procure better pricing if possible prior to any commitments or submittals to the client.
-
The selected supplier will then be submitted to the client for approval. This step is completed by the department head or assigned to one of his senior staff members.